Installation Guide LP33 Series 80 & 100 UL S1

3 INSTALLATION

3.1 TRANSPORT

The UPS is fixed on transport socket suitable for forklift, which includes a special layer of Ethafoam to
protect the equipment against the transport shock.
Normally the UPS is packaged with carton box.
On request the equipment can be packaged in wooden case.

Move the UPS in its original package to the final destination room.
Do not stack other package on top: they could damage the upper side of the cabinet.

NOTE !

When moving the UPS, pay attention to:

FRAGILE

SENSITIVE

TO DAMPNESS

TO HEAT

SENSITIVE

TO FROST

SENSITIVE

Forklift
The UPS may be lifted with a forklift in upright
position from right and left side.
Take note of the centre of gravity marked on
the package.

NOTE !

Check for sufficient floor and elevator
loading capacity.
Transport UPS only in upright position.
Do not stack other package on top of the
UPS.

Forklift

Crane

Fig. 3.1-1 LP33 Series 80 & 100 lifting

Crane
If the UPS has to be lifted by crane, use
suitable carrying belts taking note of the
centre of gravity marked on the package.
Take all necessary precautions to avoid
damage to the cabinet while hoisting the
UPS

WARNING !

When loading / downloading and when
moving the UPS, it is forbidden:

When loading / downloading and when
moving the UPS, pay attention to: