7 inter cabinet connections, 1 cabinets positioning and interconnection, Inter cabinet connections – GE Industrial Solutions SG Series 750 T12 UL S2 Installation Guide User Manual

Page 20: Cabinets positioning and interconnection, Inverter cabinet rectifier cabinet

Advertising
background image

Modifications reserved

Page 20/49

OPM_SGS_ISG_M75_M75_2US_V010.doc

Installation Guide SG Series 750 UL S2 & SG Series 750 T12 UL S2

3.7

INTER CABINET CONNECTIONS



3.7.1 Cabinets positioning and interconnection

NOTE !

The inverter cabinet and rectifier cabinet must be installed on leveled floor.



SG Series 750 & SG Series 750 T12 unit, in standard version, are delivered split into two cabinets.

Align them together with the rectifier cabinet on the right side (cabinet with control panel).
Pay attention, that no loose cables are trapped when pushing the cabinets together.

Inverter cabinet

Rectifier cabinet

190mm

7.

5"

680mm

26

.8

"

g

Rectifier cabinet frame

Spacer (aluminium)

M8 flat washer
Bolt M8x60

Inverter cabinet frame

M8 Nut with washer

Detail showing the interconnection of the inverter
and rectifier cabinets. To bolt only on the front side.

275mm

10

.8

"

SGS_750_S2_UPS connection cabinets_GE_03US

Fig. 3.7.1-1 Cabinet positioning and interconnection



Once finally positioned, the two cabinets have to be connected together with power and control wiring.
See Section 3.7.2 and 3.7.3.