Installation
6
Installation of Option Card
Please follow the installation procedure described as follows. Please install or detach the option after turning
off the input power supply of the inverter and confirming the charge lamp (CHARGE or CRG) is gone out.
The shape, the dimensions and the position of the charge lamp of the inverter are different by each capacity.
Keypad
Keypad
Option Unit
Top Cover
PE Line
Inverter Unit
Inverter Unit
Step
1
Step
2
to
4
Charge Lamp
Step 1
Loosen two screws (M4) at a and remove the top cover. Loosen two screws (M3) at b and detach the keypad
panel. (For the 30kW[40HP] and above inverters, the keypad panel can be detached if the front cover is
removed and the screws loosened at b.)
Step 2
Reassemble the top cover, push-in the option unit and secure it with two screws (M3) at c.
Step 3
Secure the keypad panel to the option unit with two screws at b.
Step 4
Connect the ground cable to the PE terminal of the option unit (The rightmost screw terminal, besides the
RJ45 Ethernet connector).