Infinity D Power System Installation Guide: +24V Systems

H2007001

Issue 2.0, June 4, 2009

38

Step

Action

3.

Secure the Hot Lead for each battery string, starting from the middle of the bay and working to
the outside. Use a double hole lug with holes on 1 inch centers.

















Hardware list for each termination is:
(2) 801273129 3/8-16 x 1in bolt
(2) 801829607 3/8-inch lockwasher
(2) 802841635 3/8-inch flatwasher

If required by local code or practice, treat with an oxidation inhibitor such as NO-OX.
Note: Landings are compatible with lugs with 1” hole spacing for 3/8” hardware.

4.

Use 9/16” socket. Torque each bolt to 240 in·lbs or 27Nm

5.

Replace Cover

6.

Re-torque screws to ~6 in·lbs ( 0.5 Nm)

7.

Loosen the four screws that secure the Return Termination cover located on the right side of the
Battery Connection Module.