Y type & basket type strainers – ClimaCool IOM AR2 SERIES User Manual

Page 27

Advertising
background image

25

www.climacoolcorp.com

®

CLIMACOOL Y TYPE & BASKET TYPE

STRAINERS

Strainer Installation Instructions:

A . Ensure all machined surfaces are free of defects and that

the inside of the strainer is free of foreign objects .

B . The strainer should be installed so that the drain

connection is pointed downwards .

C . For flanged end strainers, the flange bolting should be

tightened gradually in a back and forth clockwise motion .

Threaded end strainers should use an appropriate sealant .

D . Once installed, increase line pressure gradually and check

for leakage around joints .

E . If the strainer is supplied with a start-up screen, monitor

pressure drop carefully .

IMPORTANT! Ultimate responsibility for strainer and

material selection rests with the end-user or facility

manager, as only the end-user or facility manager knows

the particular application and operating parameters to

which the strainer will be subjected.

CAUTION: PRIOR TO DISMANTLING THE

STRAINER FOR CLEANING, IT IS IMPERATIVE

THAT THE STRAINER ASSEMBLY IS ISOLATED AND

COMPLETELY DE-PRESSURIZED.

Strainer Removal Instructions

A . Drain piping .

B . Vent line to relieve pressure .

C . Loosen flange bolts (flanged ends) .

D . Secure necessary lifting equipment to strainer assembly .

E . Remove inlet/outlet flange bolts (flanged end), or

unthread (threaded ends) and carefully remove strainer .

F . Tighten cover . The strainer is ready for line start-up .

For Basket Strainers, Follow Steps G through L .

G . Drain piping .

H . Vent line to relieve pressure .

1 . Loosen cover and open to access basket .

J . Remove, clean and replace basket in original position .

(Note: In some instances, a high pressure water jet or

steam may be required for effective cleaning) .

K . Inspect cover gasket for damage . If necessary, replace .

(Note: If spiral wound gaskets have been used, they must

be replaced and can be used again) .

L . Tighten cover . The strainer is ready for line start-up .

Y Type & Basket Type Strainers

CAUTION SHOULD BE TAKEN DUE TO POSSIBLE

EMISSION OF PROCESS MATERIAL FROM PIPING.

ALWAYS ENSURE NO LINE PRESSURE EXISTS

WHEN OPENING COVER.

Maintenance Instructions

For maximum efficiency, determine the length of time

it takes for the pressure drop to double that in the clean

condition. Once the pressure drop reaches an unacceptable

value, shut down line and follow the "Strainer Removal

Instructions" above.

A pressure gauge installed before and after the strainer in-

line will indicate pressure loss due to clogging and may be

used to determine when cleaning is required.

Trouble Shooting Guides and Diagnostic Techniques

A . After pressurizing, inspect cover and other joints for

leakage . Gasket replacement or cover tightening is

necessary if leakage occurs .

B . If the required filtration is not taking place, ensure the

screen is installed in the correct position, and that the

screen is mounted flush to the upper and lower seating

surfaces .