27

www.climacoolcorp.com

®

compressor has correct rotation . Use pressure gauges to

verify proper rotation . Always use proper electrical safety

precautions .

4 . Slowly close the chiller water inlet isolating valve and note

that the flow switch stops the machine . Note the flow rate at

which this occurs . If too much flow is lost before chiller is

stopped, reset switch setting . The flow switch should be set so

the chiller shuts down when the flow rate to each evaporator

and condenser water circuits drops below 60% of rated ARI

full load conditions (indicating a 10°F temp . change through

both the evaporator and condenser heat exchangers) .

5 . Repeat the tests of all other safety interlocks which may be

connected .

6 . The anti-freeze thermostat for each module should be set to

trip when the leaving chilled water temperature drops below

38°F .

Start Up

An anti-short cycle timer protects the chiller and there will be a

delay before the controller will allow the compressors to start .

1 . If the chilled water temperature is above the normal operating

level, all load should be removed from the chilled water

system and the suction temperature should be monitored to

prevent high current draw .

2 . If the condenser water temperature is below the normal

operating level, ensure that the condenser water temperature

control is in the correct position . Start Up

3 . Re-install all fuses and set the controller .

4 . When all temperatures are within operating limits, all high

and low pressure safety switches should be tested for each

refrigeration system .

5 . The condenser temperature controller should be checked .

Once stable conditions have been achieved, the refrigeration

system’s high and low pressures, compressor amp draw,

voltage Input level, and water system temperatures and

pressures should be logged for each chiller module separately .

6 . Check that oil level is between 1/3 and 1/2 of the sight glass .

See page 51, Oil Levels .

7 . The action of the controller should be checked for correct

operation and control .

Mechanical and General

All covers, panels and doors should be in place and secured .

Start Up Documentation

All start-up paperwork and documentation must be submitted to

ClimaCool .