PRE-START UP

Before the chiller is started, there are certain essential checks

which must be carried out . Failure to carry out these checks could

result in damage to the chiller voiding the warranty .

Electrical

It is imperative to turn off the main electrical power supply and

follow proper lock-out, tag-out procedures prior to servicing any

of the chiller’s electrical components . The following procedures

can be performed only after the electrical power is confirmed to

be off:

1 . The installation should have been inspected and approved by

the respective agent and found to be in compliance with all

local and national electrical codes .

2 . Check & tighten as required all electrical terminal connections

on each module . Utilize lock-out/tag-out procedures for this

operation . A systematic tightening of all terminals inside the

electrical control panel on each module should be carried

out . This will include the compressor motor terminals, which

would require removal of the compressor terminal cover .

Check connections at each safety and every termination in the

panel .

3 . There are approx . (12) control wires which must be field

connected from each module’s electrical panel back to the

“Master Control Panel” . These control wires should be routed

using a series of twisted pair conductors having #18 AWG

minimum up to 50 ft ., #16 AWG minimum up to 100 ft ., and

#14 AWG min . up to 250 ft . All field wiring must be identified

(tagged) .

4 . All field connections should be checked for tightness .

5 . Check all fuses for proper sizing as indicated on the chiller

data plate and/or the electrical diagram on the inside door of

the electrical panel .

Refrigeration

1 . Remove the front and rear access covers from the top

compressor sound enclosure of each module .

2 . Refrigerant piping and components should be inspected for

damage .

3 . Check all refrigeration and water valves for proper

positioning; once completed mark refrigerant valves with

permanent marker . Make sure all refrigerant valves are fully

opened and there are no visible signs of refrigerant leaks . Pre-

Start Up

4 . Place refrigerant gauges on the discharge and suction access

ports of each refrigerant circuit to ensure a refrigerant charge

is present . Leave the gauges on for compressor rotation check .

5 . Confirm the settings on all pressure switches and thermostats .

Water System

1 . Confirm that leak testing has been carried out .

2 . Confirm that the system is clean .

3 . Confirm that necessary water treatment systems are in place

with both the evaporator and condenser water systems .

4 . Confirm that appropriate water analysis has been conducted

by the end-user .

5 . Confirm that the results of this water analysis does not conflict

with the acceptable constituent ppm levels as indicated in

Table 1, page 16 .

6 . Extract a water sample from both the evaporator and

condenser . Confirm that the sample bottles are filled to the top

leaving no air in the bottles . Both sample bottles must have

labels filled out per instructions included with bottles . Mail

bottles immediately to the appropriate water testing laboratory

as per instructions included with bottles .

7 . Confirm that both the chilled water and condenser water

circulating pumps are operational and water is flowing

through both exchangers .

8 . Shut entering water valve and blow out some water to check

for particles or coloration from suspended particles . Record

the differential pressures across the chiller condenser water

header and across the condenser heat exchanger, measured at

the “Pete’s” ports at each module .

9 . Confirm correct water flow rates through the condenser

and evaporator . Acquire the “predicted” flow rates from

the building’s “hydronics system balancer” . Compare the

measured differential pressures from step 6 above with the

predicted flow rates to ensure proper correlation to the flow

results .

Chiller Pre-Start-Up Procedures

1 . Turn selector switches on module panel off . Fill in circuit

# and power panel identification inside each Module cover

panel .

2 . Ensure the correct fuses are installed in the control

transformer fuse blocks inside each ClimaCool Module . Turn

on the power to each module . The “Power” light should be on .

3 . Override output with DX commissioning program or place

a jumper between compressor 1 start terminals on the “field

wiring” terminal strip (terminals 8 &9) . With jumper in

place, turn on the selector switch marked “compressor #1”

to bump the compressor and check for proper rotation .

Use pressure gauges to verify proper rotation . Once this is

complete and correct rotation is verified, override output

with DX commissioning program or place a jumper between

compressor 2 start terminals on the control terminal strip

(terminals 10 & 11) . Turn on the switch marked “compressor

#2” to bump the compressor and verify that circuit #2

Pre-Start Up