11 system installer start-up, Initial system power check, System operation check – Hale CAFS Attack User Manual

Page 48: For foamlogix

Advertising
background image

Start Up Check List

48

CAFS Bottled-Air Operator/s Guide

p/n: 029-0020-85-0

4.11

SYSTEM INSTALLER START-UP

When energizing the CAFSAttack system at the system installer facility for
the first time the following procedures shall be used.

Initial System Power Check

1.

To check the HIGH pressure lines, SLOWLY open the cylinder shut-off
valve to gradually pressurize the HIGH pressure side of the system.
(See Figure 4-1: “CAFSAttack System Overview,” on page 25.)

2.

Check each connection for leaks.

If a leak is detected immediately CLOSE the cylinder shut-off valve,
bleed pressurized air from the system and repair the leak before return-
ing the system to operation. See Section 6.3, heading “Relieving HIGH
PRessure” on page 59.

3.

Repeat preceding Steps 1 and 2.

System Operation Check

After initial system power-up, CAFSAttack, and the FoamLogix systems
must be checked.

For FoamLogix

See the specific FoamLogix manual used in your CAFSAttack system:

FoamLogix Model 2.1A Installation and Operation Manual, Hale p/n:
029-0020-74-0

FoamLogix Model 3.3 and 5.0 Installation and Operation Manual, Hale
p/n: 029-0020-68-0

Follow the procedures outline in the separate FoamLogix manual,
headings:

Start Up Check List

Installation and Delivery Check List

System Installer Start-Up

User (Setup) Calibration

Advertising