Wall mounting racks using vibration pads, Floor mounting racks using vibration pads, N o t e – ETC Sensor3 CE (ESR3) Rack User Manual

Page 16

Advertising
background image

8

Sensor3 CE Rack (ESR3) Installation Manual

Wall Mounting Racks Using Vibration Pads

Vibration damping fittings are available as an option

for wall mounted racks. The wall must be strong

enough to hold the racks. Please see

Appendix A:

Sensor3 CE Rack Specifications, page 34

for rack

and module weights.

Step 1:

Mark the hole locations on the wall from

Figure 2: ESR3-12 and ESR3-24 wall

mount hole diagrams on page 5

.

Step 2:

Align the center of the fitting over the hole locations from the diagram. Mark the

position for two fitting bolts for each vibration pad (the middle holes are

recommended).

Step 3:

Drill the holes and secure the fittings to the wall. You must supply your own M10

mounting hardware.

Step 4:

Remove the included bolt and washer from each vibration fitting.

Step 5:

Position the rack on the wall so the centers of the vibration fittings align with the

wall mounting slots.

Step 6:

Secure the rack to its vibration pad with the included bolts and washer.

Floor Mounting Racks Using Vibration Pads

ESR3-36 and ESR3-48 racks can be floor mounted on

optional vibration damping fittings (ETC

Part# HW6109).

Step 1:

Determine where your rack will be installed

using

Figure 1: Sensor3 rack clearances on

page 4

.

Step 2:

Use the appropriate diagram from

Figure 3: Hole diagrams for mounting racks

N o t e :

Be sure this mounting method complies

with your countries building and electrical

codes.

N o t e :

ETC’s wall mount vibration pads (ETC

Part# HW6111) attach to racks with the

provided bolts that are slightly larger than

the top of the keyhole slots. The bolt works

fine installed in the lower portion of the slot,

but the rack will mount slightly higher

(approx. 10mm) than the diagram indicates.

C A U T I O N :

Unless the all mounting and connections are done in a flexible manner, the

effectiveness of the vibration pads will be reduced or completely negated. This

includes the use of at least 30cm of flexible conduit or flexible cable for all of the

electrical connections to the rack(s).

N o t e :

Be sure this mounting method complies with

local building and electrical codes.
Level racks before marking the hole positions.

Figure 4: Positioning a vibration pad

on a wall

Align the center of the fitting over the diagram

hole location and mark the position of the fitting

bolts

50cm

50cm

25cm

25cm

ETC Part# HW6111

Figure 5: Floor vibration pad

Center the fitting over the mount hole location

from the diagram and mark the positions for the

fitting hardware

ETC Part#

HW6109

38mm

38mm

Advertising