Connect line power wiring, Preparing line feed cable – ETC Sensor3 CE (ESR3) Rack User Manual

Page 20

Advertising
background image

12

Sensor3 CE Rack (ESR3) Installation Manual

Connect Line Power Wiring

ETC recommends routing line (feeder) cables first,

load neutral and load earth wires next, and load

phase wires last.

Preparing Line Feed Cable

Line cable and power wire should enter the rack

through the designated top and bottom access

points.

Line feed wires connect on the rack’s line phase,

neutral and earth bus bars. Each bus bar has one or

two 12mm studs to secure a lug connection for the

line feed wires. The installer must provide the line

feed connecting lugs.

Pull the line phase, neutral and earth cables to the

rack through the openings you prepared previously.

See “Rack Cabling Access” on page 11.

Step 1:

Pull the line phase, Neutral and Earth

cables to the rack through the openings

you prepared previously.

Step 2:

Cut the wires to length such that they

reach the correct stud

Step 3:

Prepare the end of the wire and fit the

desired termination.

Step 4:

Attach the lug to the correct phase,

neutral or earth stud as shown in

Figure 9: Line and Load Connections on

page 12

.

Step 5:

Tighten the lugs to 59.5Nm.

C A U T I O N :

Line and load wires used with Sensor3

dimming systems must be copper. Do not

use wire containing aluminium or other

metals.

C A U T I O N :

Dress wires neatly and avoid leaving extra

wire inside the rack. Too much clutter

(especially along the right side of the rack)

can restrict air circulation and reduce

cooling efficiency. If cabling interferes with

airflow during operation, the rack may shut

down due to overheating.

Figure 9: Line and Load Connections

L1

connections

Line Neutral

connections

L2

connections

Load Neutral

lug

L3

connections

Load Earth

lug (behind

phase lug)

IEC Connector

for NEFM

(optional)

Line Earth

connections

Load Phase

lug