I N S T A L L A T I O N

Left Side Blower and Monitor Arm Installation

Version 3

In Ground Model 200iPX/250iPX Motorcycle Dynamometer Installation Guide

2-21

I

NSTALLING

THE

M

ONITOR

S

UPPORT

AND

THE

J

UNCTION

B

OX

1

Place the blower mount where you installed the Red Head anchors on page 2-20.

2

Secure the blower mount, monitor support arm, and junction box to the pit floor
using four 3/8 x 1-inch bolts and four washers.
Note: The left blower mount is secured under the support arm.

3

Verify the blank plate is secured to the junction box as shown in Figure 2-13.

4

Verify the fan connectors are secured to the junction box in the location shown in
Figure 2-13.

Figure 2-13: Install the Monitor Support Arm and Junction Box

PD197

support arm

junction box

blower mount

(under support arm)

fan connectors

blank plate

Advertising