Frame may be installed as panel units, Screw spline and shear block systems installation – EFCO 403 Series Storefront User Manual

Page 67

Advertising
background image

EFCO CORPORATION 1/2013 PART NO. Y001

Page 67 of 94

Series 401,402, & 403 Installation Instructions

If an entrance is required, install the framing units starting at the
entrance frame and work towards the end of the opening.

Fig. # 70

Fig. # 71

NOTE:

SCREW SPLINE AND SHEAR BLOCK
SYSTEMS INSTALLATION

Apply sealant to the upturned flashing leg cavity as shown in

FRAME MAY BE INSTALLED AS PANEL UNITS.

Locate the first unit into position tight against the flashing back leg.
Be sure the unit is plumb and square.

Shim the jamb and head as required, and then secure them to the

See pages 68 through 70 for anchoring procedures.

Install the remaining panels in a similar fashion, snapping them

SECTION IV: C.

STEP 9)

STEP 10)

together. See Fig. # 70 and # 71 below.

structure.

STEP 8)

STEP 7)

Fig. # 67 on page 65.