Series 401,402, & 403 Installation Instructions

TILT LAST VERTICAL INTO
POSITION AGAINST CAN FILLERS

Fig. #99

Tap vertical mullion tight against the can fillers already in place,

TYPICAL ELEVATION

mullions. Check every third mullion for correct spacing.

Install the last can filler of a run before the second to last.
This will allow the tilting of the last vertical mullion into place,

MULLIONS INSTALLED TO HERE

which will then finish the run. See Fig. #99 below.

and then repeat the installation of the next can fillers and vertical

NOTE:

CAN FILLERS HELD UNTIL

LAST VERTICAL INSTALLED

CAN FILLERS & VERT.

CAN FILLERS INSTALLED

CAN SYSTEM

PREPARATION / INSTALLATION