Powering Up the Development Board

Install the Altera Quartus

®

software on the host computer, if not

already installed

The Cyclone II FPGA Starter Development Board includes an
integrated USB-Blaster™ chip set for programming the FPGA. Install
the Altera USB-Blaster driver software on the host computer, if not
already installed.

1

Communication between the computer host and the
development board requires Altera USB-Blaster driver software
already installed on the host computer.

Powering Up the
Development
Board

To power up the development board, perform the following steps:

1.

Connect the USB-Blaster cable from the host computer to the
USB-Blaster port on the development board.

2.

Connect the 7.5 V DC adapter to the development board and to a
power source.

3.

Connect a VGA monitor to the VGA video port on the development
board.

4.

Connect a headset to the Line Out audio port on the development
board.

5.

Slide the RUN/PROG switch on the edge of the development board
to the RUN position.

6.

Turn the power on by depressing the ON/OFF switch on the
development board.

Confirming
Board Operation

As the development board powers on, verify correct operation by
performing the following steps:

1.

Confirm that all user LEDs are flashing.

2.

Confirm that all 7-segment displays cycle through numbers 0
through F.

3.

Confirm that the VGA monitor displays the default image
(

Figure 2–2

) with the SW0 switch set to the DOWN (toward the

edge of the board) position.