An IRF fabric has only one master switch. You configure and manage all member switches in the IRF

fabric at the CLI of the master. IRF member switches will automatically elect a master. You can affect the
election result by assigning a high member priority to the intended master switch. For more information

about master election, see H3C S9800 Switch Series IRF Configuration Guide.
Prepare an IRF member ID assignment scheme. An IRF fabric uses member IDs to uniquely identify and

manage its members, and you must assign each IRF member switch a unique member ID.

Planning IRF topology and connections

Connect the IRF member switches through IRF ports, the logical interfaces for the connections between

IRF member switches. Each IRF member switch has two IRF ports: IRF-port 1 and IRF-port 2. To use an IRF
port, you must bind a minimum of one physical port to it.
When connecting two neighboring IRF member switches, you must connect the physical ports of IRF-port

1 on one switch to the physical ports of IRF-port 2 on the other switch.
A two-member IRF fabric must use the daisy chain topology.

Figure 56 Daisy chain topology

Identifying physical IRF ports on the member switches

Identify the physical IRF ports on the member switches according to your topology and connection

scheme.
On H3C S9800 switches, only 10-GE/40-GE/100-GE ports can be used for IRF connection.
The H3C S9800 switches support multi-card link aggregation for IRF ports. You can bind up to eight

physical ports to one IRF port.

Installing IRF member switches

Step Reference

1.

Prepare the installation site.

See "Preparing for installation."

2.

Mount the IRF member switches to racks.

See "Installing the switch."

3.

Install modules on IRF member switches.

See "Installing FRUs."