Installing the l1000-a, Confirming installation preparations – H3C Technologies H3C SecPath L1000-A Load Balancer User Manual

Page 17

Advertising
background image

9

Installing the L1000-A

IMPORTANT:

Keep the packages of the L1000-A and the components for future use.

Figure 3 L1000-A installation flow

Confirming installation preparations

Before you install the L1000-A, verify that:

You have read "

Preparing for installation

" carefully and the installation site meets all the

requirements.

A 19-inch rack is ready for use.

The rack is sturdy and securely grounded.

There is sufficient clearance around the rack for heat dissipation and installation.

No debris exists inside or around the rack.

Choose a correct rack mounting position for the L1000-A. Make sure the heaviest device is placed
at the bottom of the rack.

Advertising