Commissioning

Honeywell

Honeywell

Honeywell

Honeywell

8

9

Run the start-up tests without the motor being connected to the process, if possible. If this is not

possible, secure the safety of each test prior to running it. Inform your co-workers of the tests.

a)

Switch off the supply voltage and wait up until the drive has stopped as advised at Chapter 8.1,
step 5
.

b)

Connect the motor cable to the motor and to the motor cable terminals of the frequency converter.

c)

See to that all Start/Stop switches are in Stop positions.

d)

Switch the mains ON

e)

Repeat test 8A or 8B.

10

Connect the motor to the process (if the start-up test was run without the motor being connected)

a)

Before running the tests, make sure that this can be done safely.

b)

Inform your co-workers of the tests.

c)

Repeat test 8A or 8B.