Stacking Recommendations

The purpose of this section is to collect notes on recommended procedures and expected behavior
of stacked managed switches. Procedures addressed initially are listed below.

•

Initial installation and power-up of a stack.

•

Removing a unit from the stack

•

Adding a unit to an operating stack

•

Replacing a stack member with a new unit

•

Renumbering stack members

•

Moving the master to a different unit in the stack

•

Removing a master unit from an operating stack

•

Merging two operational stacks

•

Preconfiguration

•

Upgrading firmware

•

Migration of configuration with a firmware upgrade

General Practices

•

When issuing a command (such as move management, or renumber), it is recommended that
the command has fully completed before issuing the next command. For example, if a reset is
issued to a stack member, use the show port command to verify that the unit has re-merged
with the stack, and all ports are joined before issuing the next command.

•

When physically removing or relocating a unit, always power down the unit before
disconnecting stack cables.

•

When reconnecting stack cables, connect them before powering up the unit, if possible, and
insure a good connection by tightening all connector screws (where applicable).