INSTALLATION

19

PNEG-1521 Commercial Direct Gear Drive Bin Sweep Auger

6. CENTERWELL CONTROL GATE ASSEMBLY

Centerwell

Control Gate

Centerwell

Control Rod

Flat Washers

5/16” Serrated

Flange Nuts

1/2” Control Rod

Clamp

5/16” x 3/4”

Carriage Bolts

A. Close the Centerwell Control Gate completely.

B. Align the Centerwell Control Rod between the two

holes in the Centerwell Control Gate.

C. Attach the ½” Control Rod Clamp to the

Centerwell Control Rod by sliding 5/16" x 1-¾” roll
pin through the Clamp and the Rod.

D. Fasten the Control Rod Clamp to the bottom side

of the Centerwell Control Gate by using two
(2) 5/16" x ¾” Carriage bolts, flat washers, and
Serrated Flange nuts. Install the nuts so that they
secure the roll pin in place.

Inside Intermediate

Well Control Rod

Holes are Aligned

and Horizontal

Centerwell

Control Rod

Outside Intermediate

Well Control Rod

E. Adjust the Centerwell Control Rod and the

Intermediate Control Rods so that the second hole
on the Centerwell Control Rod and the hole on the
Intermediate Control Rod are aligned, and that
they are both horizontal.

This alignment is important for

proper gate control with the

Rack & Pinion.

5/16” x 1-3/4”

Roll Pin

FIG. 6-A

FIG. 6-B

F. Make sure all connections are tight.