Rack & pinion installation – Grain Systems Unload Augers PNEG-1521 User Manual

Page 21

Advertising
background image

INSTALLATION

21

PNEG-1521 Commercial Direct Gear Drive Bin Sweep Auger

A. Make sure that all gates are fully closed.

B. Pin the Inside Intermediate Control Rod to the

Centerwell Control Rod, by using a 5/16" x 1-¾”
Hex bolt and Hex nut through the aligned hole.

8. RACK & PINION INSTALLATION

C. Slip the Rack & Pinion tube over the Centerwell

Gate Control Rod, and slip the Outside
Intermediate Well Adapter pipe into the Outside
Intermediate Control Rod. Align the holes to the
Centerwell Control Rod and the Outside
Intermediate Well Control Rod with the matching
holes on the Rack and Pinion. Make sure the
Rack & Pinion is fully extended towards the bin
wall.

D. Attach the Rack & Pinion to the Control Rods

using two (2) 5/16" x 1-¾” Hex bolts and Hex nuts.

FIG. 8-A

FIG. 8-B

FIG. 8-C

Advertising