2.6 Grounding

Requirements

The ground rod system is typically used in remote applications where the generator is located
away from the power supply enclosure and exposed to lightning strikes, or coincidental
surges. The wiring interface between the DC Genset and system carries a system ground to
ensure common ground between both cabinets and communication devices. The remote APU
cabinet ground rod serves only as an alternate discharge path.

A •

8 feet long, 1/2 inch diameter copper electrode.

To aid in serviceability, place the ground electrode outside the concrete pad’s perimeter.

Consult local utility codes for additional cabinet grounding and utility requirements.

B •

#6AWG bare copper wire exposed 5 feet above grade (min.) for output ground bus bar.

Clamp #6AWG bare copper wire exposed 5 feet above grade (min.) for output ground bus

bar.

Fig. 2-8, Grounding Requirements

A

B

Conduit

AC In

DC Out