7. Press and hold the ECM’s RAS switch in the STOP position until the generator stops.
8. Disconnect the DWYER # 1212 manometer gas pressure test kit from the secondary
demand regulator.
9. Reapply a small amount of an approved pipe sealant to the Allen-head cap screw,
replace and tighten into the demand regulator.
10. Replace the Maxtrol regulator access cap and gasket, and tighten.
7.0 Maintenance,
continued
7.9
Maxitrol Pre-regulator Calibration, continued
6. Verify the DWYER # 1212 manometer reads 5-1/2" above the “0” mark, and 5-1/2" below
the “0” mark. This equals 11" water column of pressure. Adjust the Maxitrol regulator in a
clockwise direction to increase pressure, and in a counterclockwise direction to decrease
pressure.
Do not bottom out the regulator adjust screw. If you cannot get a reading, retest the inlet pressure to the
Maxitrol gas package.