Initial Administration

This section describes the tasks required to initially administer the DEFINITY
LAN Gateway system. It is expected that these procedures will be performed by
AT&T services personnel upon completion of the hardware installation.

Preliminary to installation, the Project Manager should complete the form located
in Appendix G. After the system is installed, the Project Manager calls the TSC
to register the system.

The tasks for initializing the system are as follows:

Task 10: Perform initial switch administration

Task 11: Perform initial DEFINITY LAN Gateway administration

Task 12: Reboot the MFB

Task 13: Test LAN/Client connectivity (optional)

Task 14: Register/back up the system

Task 10: Perform Initial Switch
Administration

Initial system administration involves the customer administering the DEFINITY
LAN Gateway circuit pack on the switch with the DEFINITY change
circuit-packs
command. Follow the steps listed below.

NOTE:

ASAI must be enabled on the DEFINITY Customer Options form for the
system to be fully operational. For more information on switch
administration, see

DEFINITY Communications System Generic 3 V4

Implementation, 555-230-655.

1. Access the change circuit-packs form. A screen similar to the one below

appears. This screen shows the Multi-Function board entered in slot 6.

Issue 1 January 1996