Setting the closing time
S
Tighten the restrictor screws of the upstream GRLA-... /GRLZ-...
– at first completely
– then open again approximately one turn.
S
Start a test run in the sequence specificed below:
Test run
Checks to be made
Without work load
– Compressed air connections must be assigned cor-
rectly
– Gripping speed
– Sensor functions
With work load
– Work load must be held firmly
Fig. 20
1. Listen to the knock of the piston.
Piston knock
Soft
Metallic
Tighten the restrictor screw one turn.
The maximum gripping speed has been reached.
Continue test run with points
2 and 3
Conclude test run.
Fig. 21
2. Loosen the restrictor screws of the upstream GRLA-... / GRLZ-... by one turn.
3. Repeat points 1 and 2 until the desired gripping speed is reached.
S
Conclude the test run.
S