SECTION 3 - CHASSIS & TURNTABLE

3-54

– JLG Lift –

3121160

6. The Bearing Cone (1F) is an interference fit and has

to be pressed or tapped on.

7. Pipe Plugs (1J & 1K) should be checked and/or

installed at this time in the assembly.

8. Bearing Spacer (1H) is installed around the Output

Shaft (1A) and locates on Bearing Cone (1F).

9. Retaining ring (11) installed into the groove provided

in the Output Shaft (1A). This Retaining Ring (1l)
should never be reused in a repair or rebuild.

EYE PROTECTION SHOULD BE WORN DURING THIS PROCE-
DURE.

10. A soft metal punch should be used to insure that this

Retaining Ring (11) is completely seated in the
groove of the Output Shaft (1A).

EYE PROTECTION SHOULD BE WORN DURING THIS PROCE-
DURE.

11. Upon completion of Step 10, rap the internal end of

the Output Shaft (1A) twice with a piece of soft metal
rod. This will release the preload which was on the
Bearings.