Installation check

6

l

136

EDKCSCX064 DE/EN/FR 4.0

6

Installation check

After the installation has been completed, check the wiring with regard to
completeness, short circuit, and earth faults:

ƒ

Power connection:
Polarity of the DC−bus voltage supply via terminals +UG, −UG

ƒ

Motor connection:
In−phase connection to the motor (direction of rotation)

ƒ

Wiring of "safe torque off" (formerly "safe standstill")

ƒ

Feedback system

ƒ

Control terminals:
Wiring adjusted to the signal assignment of the control terminals.

)

Note!

The next step is the commissioning. Relevant information can be
found in the mounting instructions of the ECS axis module.

ƒ

Read the mounting instructions before switching on the axis
module.

ƒ

Carry out the commissioning according to the instructions in the
mounting instructions.

ƒ

If you use the "safe torque off" function, you must check the
function of the circuit.