Pre-hung arch/radius unit installation – Therma-Tru Doors Installation User Manual

Page 19

Advertising
background image

Installation

SITE 1

2014

1.19

Pre-Hung Arch/Radius Unit Installation

1

Equ

al

Eq

ua

l

Check all

four corners

with square

Wall straight?

Check

each side

both ways

Wall straight?

Check floor

under sill

Compare Diagonals

Is subfloor level and solid? Provide a flat, level clean bearing

surface so the sill may be caulked and sealed to the opening.

Scrape, sand, or fill as required.

Shim subfloor for floor covering clearance if required. If

shimming, caulk under shims.

Is opening square? Check all corners with a framing square.

Double-check by comparing diagonal measurements. Fix any

problems now.

Are framing and walls plumb? Use a 6-foot level and check both

sides of opening, both ways. Fix any problems now.

Are the wall surfaces around the opening on the same plane?

There must be no “warps” or “jogs”. Fix any problems now.

size now

before installation. Opening should be frame height plus ½” and

frame width plus ½” to 1”.

• Is opening correct size? Check it against door frame

2

Build support framing at top for radius/arched top head

jamb as shown below

Pre-hung Rustic Arch/Radius

Installation Instructions

CHECK AND PREPARE OPENING

SUPPORT FRAME CONSTRUCTION

1

2

Refer to MSDRIST for all other Pre-Hanging Instructions

Radius Top Head Jambs

Arch Top Head Jambs

70°

5 1/32

20°

13 7/8

14 3/4

11 9/32

11 9/32

45°

45°

15 15/16