Pre-hung unit installation – Therma-Tru Doors Installation User Manual

Page 4

Advertising
background image

Installation

1.4

2014

SITE 1

Pre-Hung Unit Installation

Step 2 cont.: Check and Prepare Opening.


Check to be sure the framing walls around the

opening are in the same plane. Do this by

performing a “string test” for plumb.

String Test for Plumb: Attach a string diagonally

across the opening from the outside, as shown. The

string(s) should gently touch in the center, if not the

opening is “out of plumb” by twice that distance

and needs to be corrected. Flip the string over

itself to check both planes. Fix any problems now.

*An “out of plumb” condition is one of the most

common reasons door units leak air and water.


Step 3: Caulk the Sub Floor.

On the sub floor at opening, place 3 very large beads

of sealant. Run beads full width of the opening.

Use Only Elastomeric or Polyurethane sealant.

Use an Entire Tube when Caulking along the Sub

Floor.

Step 3A: Installation with a Sill Pan.

Place the right and left sill pan ends onto the caulk beads and tightly against

the side of the opening.

Then, liberally coat the overlapped areas and the recessed areas of the pieces

with the PVC cement provided. Place center section(s) in position and hold

pieces together long enough to ensure a good bond.

For added protection, spread a bead of caulk along the glue joints and to

prevent air infiltration, run a bead of caulk along the lower interior edge of the

sill pan. Additional caulking could affect the performance of the sill pan.

Do Not Caulk the bottom of the Sill when using a sill Pan.

Step 3B: Installation without a Sill Pan.

Lay the door unit on edge or face so

that the bottom surface of the sill

can be caulked. Place very large

beads of caulk across the full width

of the sill. Additionally, place beads

of caulk along the junction of the

sill and the jamb and on the bottom

surface of the jambs and

brickmould.

Note: If a sill extender is used, place a large bead of caulk at the junction of

the extender and the sill approach.

Step 3 cont.: Caulking Back side of Brickmould.

Important!

Apply sealant to the back side of

brickmould around the entire perimeter

of the door unit. A 1/2 – 5/8 inch bead

of Elastomeric or Polyurethane caulk is

essential.



Step 4: Place Unit in Opening and Temporarily Fasten.

Lift the unit up. With top edge tilted away from

opening, center the unit and place sill down onto

sill pan or caulk beads and tilt into opening.

For all door unit configurations, note the hinge

locations and mark those locations on the jamb

faces near the door surfaces. Pre-drill 1/8 inch

diameter holes at these locations for screw

placement. A counter sink bit will help to

conceal the screw heads.

Install screws in the center pre-drilled hole

locations on both jambs to temporarily secure

the unit in the place. Do not drive screws

completely in at this time. Use #8 X 2-1/2 inch

or 3 inch exterior grade screws.

Do Not Fasten through the Brickmould.

Step 4 cont.: Plumb Hinge Side Jamb.

Work from side of the door that is weather-stripped.

Use a 6 foot level and plumb the hinge side jamb both ways (right to left and

inside to outside).

Place screws through the hinge side jamb into the studs, at each remaining

hinge location, as shown in the diagrams. Use #8 X 2-1/2 inch or 3 inch

exterior grade screws.

Do Not drive the screws completely in at this time.

For Single or Double Doors, place screws at each hinge location, so shims can

be placed behind hinges above screws. The screws will keep the shims from

falling down while adjustments are being made.

For Sidelite units, fasten the jamb on the hinge side of the door.

For Double Door and Patio Units, fasten the fixed or passive side of the unit

first.

Single Unit Sidelite Unit Double Unit