This chapter describes how to start up the LPM20. Refer to

Appendix B

for

a brief description of the LCD HIM (Human Interface Module).

Prepare For Drive Start-Up

Before Applying Power to the Drive

Important: If you have a DriveLogix application, you must first connect

the battery before starting this procedure.

1. Confirm that motor wires are connected to the correct terminals and are

secure.

2. Confirm that encoder wires are connected to the correct terminals and

are secure.

3. Confirm that all inputs are connected to the correct terminals and are

secure.

4. Verify that AC line power at the disconnect device is within the rated

value of the drive.

5. Verify that control power voltage is correct.

The remainder of this procedure requires that a HIM be installed. If an
operator interface is not available, remote devices should be used to start
up the drive.

For information on ...

See page ...

Prepare For Drive Start-Up

2-1

Status Indicators

2-3

Assisted Start Up

2-4

!

ATTENTION: Power must be applied to the drive to perform the
following start-up procedure. Some of the voltages present are at
incoming line potential. To avoid electric shock hazard or damage
to equipment, only qualified service personnel should perform the
following procedure. Thoroughly read and understand the
procedure before beginning. If an event does not occur while
performing this procedure, Do Not Proceed. Remove Power
including user-supplied control voltages. User-supplied voltages
may exist even when main AC power is not applied to the drive.
Correct the malfunction before continuing.