Always perform the power lock-out procedure before

proceeding with servicing the equipment Use suitable

personal protective equipment (PPE) per local codes or

regulations. Failure to do so may result in severe burns,

injury or death.

The following procedure requires moving the isolation

switch handle to the ON position. To avoid shock

hazards, disconnect and lock out incoming power before

proceeding with servicing the equipment. Failure to

lock out incoming power will result in a live power cell

once the isolation switch handle is in the ON position

and may cause severe burns, injury or death. Rockwell

Automation does not assume any responsibility for

injuries to personnel who have not completed the following

safety procedure prior to servicing the equipment.

1) Disconnect and lock out all feeder power supplies to the starter.

2) Move the isolation switch handle to the OFF position.

3) If the unit is equipped with power factor correction capacitors, stored

energy must be dissipated before entering the power cell. Wait at least
fi

ve minutes before entering the power cell or dissipate the power using

the following procedure:

a) Verify that the isolation switch handle is in the OFF position.

b) Open the low voltage door.

c) Plug the appropriate power supply (120 or 230V) into the auxiliary

power receptacle on the control panel (see Figure 3.2).

d) Move the control switch to the TEST position.

Test Switch

Auxiliary Power Receptacle