4-2

Commissioning

1503-IN050E-EN-P – June 2013

Preliminary Checklist

Contactor Operation

To avoid shock hazards, lock out incoming power before

working on the equipment. Verify with a hot stick or

appropriate voltage measuring device that all circuits are

voltage free. Failure to do so may result in severe burns,

injury or death.

1) Connect the appropriate external power supply (120 or 230 VAC) to

the test receptacle in the control panel. Turn the selector switch to the

TEST position (see Figure 3.2).

2) Electrically operate the contactor several times. Inspect the armature

plate to verify that it fully contacts the cores (400A) or yolk plate (800A).

3) Turn the selector switch back to the OFF position and disconnect the

test power supply.

Electrical Connections

1) Verify correct power cable phase sequencing and that the connections

are tight. See Torque Requirements, page 1-4.

2) Verify power fuse ratings and condition.
3) Verify control fuse ratings and condition.
4) Check that components were not damaged during power cable

installation, and that electrical spacings are suffi cient.

Final Checks

1) Remove all tools from the cabinet. All tools and hardware used

during installation and commissioning must be accounted for prior to

energizing the unit.

2) Remove all temporary jumpers and grounding devices used during the

installation procedures.

3) Ensure that all barriers or covers removed during installation have been

securely reattached.

4) Close and secure all doors. Verify that all interlocks preventing access

to medium voltage power cells are functioning correctly.

Use suitable personal protective equipment (PPE) per

local codes or regulations. Failure to do so may result in

severe burns, injury or death.

5) Restore incoming power from main power supply.
6) Move the isolation switch handle to the ON position.
7) The controller is now ready to supply power to the load.