Installing the ProteinChip SELDI Reader

Page 7

Ventilation

The ProteinChip SELDI reader requires 3.0 cm of space at the rear and 3.0 cm
above the vents on the top of the main enclosure and at the top of the tower
for adequate ventilation. The air on all sides of the enclosure must meet the
environmental conditions specified above during operation. The region around
the system should be kept free of dust.

Mounting

The ProteinChip SELDI reader has no special mounting requirements. If your
location is subject to earthquakes, adequate restraints should be used to
prevent the reader from moving.

Network Connection

A network connection can be made to the computer according to the
computer manufacturers’ instructions.

Installing the
ProteinChip
SELDI Reader

Setup Time

It takes approximately one day to get the ProteinChip SELDI reader ready for
operation, including unpacking and moving the reader to the laboratory,
connecting it to the power supply, connecting a computer to the reader, and
allowing the unit to reach operating pressure. Installation is generally
performed by a Bio-Rad engineer.

Pre-Installation Reader Inspection

1.

Position the reader’s shipping case on a level surface.

2.

Release the straps at the bottom of the case, then remove the upper part of
the case. The reader is secured to the bottom part of case with four bolts
which can now be released.