C-more controller for benchmark, innovation & kc – AERCO C-More Controls Manual June 2010 User Manual

Page 124

Advertising
background image

C-More Controller for Benchmark, Innovation & KC

USER MANUAL

Page 124 of 162

AERCO International, Inc. • 100 Oritani Dr. • Blauvelt, New York 10913

04/22/14

GF-112

Phone: 800-526-0288

OMM-0032_0E

9.6.1 Option 1 - Constant Setpoint with Direct Wired Header Sensor

Step 1: Direct Wired Header Sensor Wiring

1. On the MASTER Unit, Connect the Header Temperature Sensor (AERCO PN 61040) to the

Feed Forward (FFWD) terminals on the P-1 Harness Via the terminal block labeled “Header
Temp sensor” in the I/O Box.


NOTES:

• The header sensor must be installed between 2 and 10 feet downstream of the LAST boiler

in the plant’s supply water header.

• Shielded pair 18 - 22 AWG cable is recommended for header sensor wiring. There is no

polarity to be observed. The ground for the shield is at the “SHLD” terminal in the I/O the
Box. The sensor end of the shield must be left free and ungrounded.

Step 2: Configure ALL C-More Units

On ALL Boilers:

1. Go to the Configuration Menu and set the BST Menu item to Enabled.

2. Go to the BST Menu and set the BST Mode item to BST Slave (for now).

On MASTER only:

3. Go to the BST Setpoint item and enter the desired Setpoint.

4. Go to the BST Setup Menu item and set to Enabled.

5. Go to the BST Setpoint Mode item and select Constant Setpoint.

6. Go to the Head Temp Source item and select FFWD Temp.


When ALL C-More units have been configured
:
7. Go to the BST Menu of the desired Master unit and set the BST Mode item to BST

MASTER.

Temp Sensor PN 61040

Header Temp Sensor

I/O Box

Advertising
This manual is related to the following products: