Benchmark 6000 DF Installation, Operation & Maintenance Manual

CHAPTER 7 – MAINTENANCE

OMM-0096_0B

AERCO International, Inc. • 100 Oritani Dr. • Blauvelt, NY 10913

Page 113 of 219

GF-141

Ph.: 800-526-0288

03/21/2014

Front Refractory Replacement Procedure – Continued

13.

Using a magnetized Phillips screwdriver, secure the Burner Shield to the plate using the
10-32 screws removed in step 7.

14.

Reinstall the plate, with the new refractory, onto the combustion chamber. Ensure it is
properly aligned to prevent damage to the fiber material.

15.

Reassemble the items removed in section 7.7, steps 18 through 20.

IMPORTANT

Following the replacement of the front refractory (part no. 83027), a 2 hour
burn-in period at a 30% fire rate must be performed to drive off organic
binders. These organic binders are not hazardous materials, however they
may emit an odor similar to burning wood.

Figure 7-9. Front Plate Assembly



BURNER
PLATE

FRONT

REFRACTORY

BURNER

SHIELD