AERCO BMK 6000 Dual Fuel User Manual

Page 19

Advertising
background image

Benchmark 6000 DF Installation, Operation & Maintenance Manual

CHAPTER 2 – INSTALLATION

OMM-0096_0B

AERCO International, Inc. • 100 Oritani Dr. • Blauvelt, NY 10913

Page 19 of 219

GF-141

Ph.: 800-526-0288

03/21/2014

Remove the four (4) lag screws securing the unit to the shipping skid, and, if still in place,
remove the front and rear Top Panels. Lift the unit off the shipping skid and position it on the
concrete Housekeeping Pad (required) in the desired location.

WHEN LIFTING OR MOVING THE BOILER: DO NOT ATTEMPT
TO MANIPULATE THE BOILER USING THE GAS TRAIN OR
BLOWER. A SPREADER BAR IS REQUIRED FOR ALL
VERTICAL LIFTS.


Figure 2-3. Boiler Lifting Provisions

In multiple unit installations, it is important to plan the position of each unit in advance. Sufficient
space for piping connections and future service/maintenance requirements must also be taken
into consideration. All piping must include ample provisions for expansion.

If installing a Combination Control Panel (CCP) system, it is important to identify the Combination
Mode Boilers in advance and place them in the proper physical location. Refer to Chapter 5 for
information on Combination Mode Boilers.

WARNING

LIFTING TABS

TOP VIEW WITH TWO TOP PANELS REMOVED

NOTE:

Remove the two top panels
to access the lifting tabs.

Advertising