AERCO BMK 6000 Dual Fuel User Manual

Page 151

Advertising
background image

Benchmark 6000 DF Installation, Operation & Maintenance Manual

CHAPTER 10 – BOILER SEQUENCING TECHNOLOGY

OMM-0096_0B

AERCO International, Inc. • 100 Oritani Dr. • Blauvelt, NY 10913

Page 151 of 219

GF-141

Ph.: 800-526-0288

03/21/2014

10.3.7 Option 7 - Remote Setpoint with MODBUS Header Sensor AND 4-20ma
Setpoint Drive

NOTE: Both Header Sensor AND 4-20ma Direct Drive must be wired. See the C-More
Controller User Manual, OMM-0032, GF-112 and ProtoNode User Manual, OMM-0080, GF-129
for more information.

Step 1: MODbus Header Sensor

1. Using Shielded pair 18 - 22 AWG cable, Connect the Temperature Transmitter (AERCO P/N

65169) terminal Pin B to the RS485+ terminal on the I/O Box of any of the Boiler units, and
Pin A of the Temperature Transmitter to the RS485- terminal on the I/O Box of any of the
Boiler units.

2. Using Shielded pair 18 - 22 AWG cable, connect the Modbus Header Temperature Sensor

(AERCO PN 24410) to pins 2 and 3 of the Temperature Transmitter.

3. Install a jumper wire between pins 1 and 2 of the Temperature Transmitter.


NOTES:

• Polarity must be observed for the RS485 connections. The ground for the shield is at the

“SHLD” terminal in the I/O the Box.

• The header sensor must be installed between 2 and 10 feet downstream of the LAST boiler

in the plant’s supply water header.

• There is no polarity to be observed. The ground for the shield is at the power supply

ground. The sensor end of the shield must be left free and ungrounded.

Step 2: Direct Wired 0-20ma or 4-20ma Wiring

1. Connect the 4-20ma or 0-20ma terminals from the Direct Drive source to the Ain+ and Ain-

terminals on the Master.


NOTES:

• Unit’s I/O Box. Shielded pair 18 - 22 AWG cable is recommended for this connection.

Polarity must be observed.

• The ground for the shield is at the driver signal source.

Temp Sensor PN 24410 Modbus Transmitter

I/O Box

I/O Box

Advertising