9.0 Final Checks

and Start-Up

9.1 General Comments

Assumptions: All connections are made; actual startup is imminent. Site

is clean; all excess supplies, scraps, and debris have been removed.

WARNING:

To prevent injury or death due to electrocution or contact

with moving parts, lock disconnect switch open when doing

checks prior to startup. See Hazard Levels, page 3.

9.1.1 Checklist Prior to Start-up

Check Clearances. All clearances must be as illustrated in Para-

graph 4.1.

Electrical Checks

Verify the electrical supply matches voltage rating of the unit.

(Refer to the rating plate.)

Check the wiring for loose connections or damaged wire. Be sure

to check the black molded plastic plug or terminal block on the

compressor. Tighten plugs and connections. Replace damaged

wiring. (See Paragraph 7.3 for replacement wiring requirements.)

Check all field wiring against the wiring diagram. Be sure all field-

installed controls are in place. Be sure that wire gauges are as

required for the electrical load. All field wiring must comply with

the National Electric Code and local regulations.

Be certain that the electrical entrances are sealed against the

weather.

Check that fuses or circuit breakers are in place and sized

correctly.

Be certain the manual reset on the compressor high pressure

cutoff switch is reset.

Check free rotation of condenser fan(s).

Remove all shipping supports and restraints.

Check field-installed refrigerant lines:

Verify that the filter driers shipped with the unit are installed prop-

erly in the correct circuits.

Verify that the refrigerant line for 1/3 circuit A on the condenser

is connected to 1/3 circuit A on the evaporator. Check that 2/3

circuit B on the condenser is connected to 2/3 circuit B on the

evaporator.

Verify that the thermostatic expansion valve bulbs are attached

properly to the correct suction line. See Paragraph 6.1.3.3.

Verify that the system has been properly evacuated and charged

with R-410A refrigerant.

In addition, verify that all startup checks in the air handling

manual have been completed.

IMPORTANT

On initial start-

up, fill-in the

CONDENSER

STARTUP FORM

on page 38.

Completed form

may be required

for warranty.