0 location 3.0 receiving, moving, and uncrating, 1 receiving 3.2 moving 3.3 uncrating, 1 shipped-separate items – Reznor MASA Unit Installation Manual User Manual

Page 5: 0 clearances and dimensions, 1 clearances, 1 receiving, 2 moving, 3 uncrating

Advertising
background image

Form I-COND, P/N 220746R6, Page 5

4.1 Clearances

The condensing unit must

have unrestricted airflow

FIGURE 1 - Minimum

Clearances (Top

View)

Coil Side

(Inlet airflow through

the condenser coil

must be unrestricted.)

Control Side

(Service

Clearance)

Opposite

Control

Side

Electrical Entrance Side

NOTE: Suggested side for installing disconnect switch;

see

FIGURE 2, page 6. If disconnect switch is installed

on this side, minimum clearance is 36” (914mm).

Airflow

Top discharge airflow must be unrestricted.

Top clearance is 60” (1524mm).

36”

(914mm)

6”

(152mm)

6” (152mm)

48”

(1219mm)

Top

View

on the coil side and above the unit. A service clearance is required on the con-

trol side of the cabinet.

2.0 Location

3.0 Receiving,

Moving, and

Uncrating

3.1 Receiving

Check for any damage that may have been incurred during shipment. If dam-

age is found, document the damage with the transporting agency and immedi-

ately contact your Reznor distributor. If you are an authorized Distributor, follow

the FOB freight policy procedures as published by Reznor for Reznor products.

3.2 Moving

The heavy gauge base of the condensing unit has forklift openings in both

sides. To move a unit, use a forklift with forks that have a minimum length of

24” (610mm).

3.3 Uncrating

Immediately upon uncrating, check the electrical characteristics to verify that

the unit is suitable for the installation site. This condensing unit is designed for

R-410A refrigerant only; verify that the split system air handler is for use with

R-410A refrigerant.

3.3.1 Shipped-Separate Items

Before beginning installation, be sure that all shipped-separate options ordered

are available at the site. Shipped-separate options could have been ordered

with the condensing unit or the matching PreevA

®

air handler.

NOTE: Two liquid line filter driers are shipped loose with the condensing unit

for field installation.

4.0 Clearances and Dimensions

Model MASA condensing unit must be mounted outdoors on a level surface.

The supporting structure must be able to support the operating weight of the

unit and maintain a level plane during continued operation. Water should drain

away from the unit. Location must comply with free space clearances for unre-

stricted airflow (See Paragraph 4.1) and the refrigerant piping requirements

(See Paragraph 6.1.3). Avoid facing condenser coils into the prevailing wind.