4 optional hot gas bypass valve, 0 maintenance and service, 1 general – Reznor MASA Unit Installation Manual User Manual

Page 26: Warning

Advertising
background image

Form I-COND, P/N 220746R6, Page 26

STEP 2) From Temperature/Pressure Conversion Chart,

APPENDIX, page 40, convert Measured Pressure (STEP
1) to ________°F (°C)

STEP 3) Subtract Measured Temperature (STEP 1) from

Temperature from Conversion Table (STEP 2)
________°F (°C) - ________°F (°C) = ________°F (°C)
degrees of Superheat

Recommended superheat is 8-12°F (4.5-6.7°C).

Typically, too much superheat indicates that the evaporator coil is

undercharged. Too little superheat typically indicates that the evapo-

rator coil is overcharged and may potentially flood liquid refrigerant

to the compressor. To reduce the superheat, adjust the thermostatic

expansion valve by turning the adjusting stem counterclockwise. To

increase the superheat, adjust the thermostatic expansion valve by

turning the adjusting stem clockwise.

9.2.4 Optional Hot Gas Bypass Valve

If the system is equipped with an optional hot gas bypass, check

operation of the valve. Set if needed. Follow the instructions in Para-

graph 8.3.3.

9.0 Final Checks

and Start-Up

(cont’d)

9.2.3 Refrigerant

Charge (cont’d)

9.2.3.1 Check

SUBCOOLING

(cont’d)

9.2 Start-up (cont’d)

10.0 Maintenance

and Service

WARNING

Turn off the power before performing all maintenance

procedures (except to check subcooling and superheat).

Lock disconnect switch in OFF position. See Hazard Levels,

page 3.

10.1 General

9.3 After Startup:

Assumptions: All checks have been successfully performed and the

system is operating properly. All panels and doors are secure. The area

has been cleared of any excess supplies, scrap, and debris.

Check that the information on page 44 has been completed.

After startup, put this manual

with completed startup form (page

41), the warranty form, and any other instructions provided with the

unit in the Literature Bag.

Return the “Literature Bag” to the low voltage compartment of the

unit or give it to the building owner for safe keeping.

This condensing unit will operate with a minimum of maintenance. To ensure

long life and satisfactory performance, an air conditioning system that is oper-

ating under normal conditions should be inspected according to the Mainte-

nance Schedule below. If in an environment where an unusual amount of dust

or soot or other impurities are present, more frequent inspection is recom-

mended.
The procedures in the schedule below are only for the condensing unit.

Refer to and comply with the maintenance schedule for the Reznor

PreevA

®

unit or other air handler with evaporator.

Advertising