Form I-COND, P/N 220746R6, Page 38

Customer Name: _______________________________ Condenser Model #: _______________________

Address: _____________________________________ Condenser Serial #: _______________________

City, State Zip: ________________________________ Air Handler Brand: ________________________

Contractor Firm Name: __________________________ Air Handler Model #: _______________________

Installing Contractor: ____________________________ Air Handler Serial #: _______________________

Remove all shipping supports and restraints (Section 3.0)

Check unit for damage (Section 3.0)

Check air flow clearances (Section 9.1.1)

Verify incoming power matches unit rating (Section 9.1.1)

Check & tighten all electrical connections (Section 9.1.1)

Check unit for proper field installed wiring (Section 9.1.1)

Check free rotation of condenser fan(s) (Section 9.1.1)

Crankcase heater ON for 24 hours (Section 9.2)

Check manual high pressure reset switch (Section 8.3.1)

Leak tested field-installed refrigerant lines (Section 6.2.2)

Check refrigerant line free from rubbing

Filter driers installed (Section 6.1.3.3)

Trap installed (if required) (Section 6.1.3.4)

System evacuated to 500 microns (Section 6.3)

Proper start-up of air handling equipment (Section 9.1)

Condenser A connected to evaporator A (B to B) (Section

6.1)

Thermostatic expansion valves properly installed (Sec-

tion 6.1.3.3)

CONDENSER STARTUP FORM

Complete on initial startup. Completed form may be required for warranty.

PRE-STARTUP CHECK LIST (

See Section References for details.)

ELECTRICAL CHECKS

PIPING CHECK

Date: __________

OPERATIONAL DATA

Operate for 30 minutes for system to stabilize

Circuit A

Circuit B

Subcooling Temperature

Liquid line temperature leaving condenser

°F(°C) °F(°C)

Liquid line pressure leaving condenser

psig

psig

Subcooling temperature

°F(°C) °F(°C)

Superheat Temperature

Suction line temperature leaving evaporator

°F(°C) °F(°C)

Suction line temperature entering condenser °F(°C) °F(°C)
Suction line pressure entering condenser

psig

psig

Superheat temperature

°F(°C) °F(°C)

Optional hot gas bypass start to open

lbs.

lbs.

Optional hot gas bypass full open

lbs.

lbs.

Test Conditions

Condenser fan entering air temperature

°F(°C) °F(°C)

Condenser fan leaving air temperature

°F(°C) °F(°C)

Evaporator entering dry bulb air temperature °F(°C) °F(°C)
Evaporator entering wet bulb air temperature °F(°C) °F(°C)
Evaporator leaving wet bulb air temperature

°F(°C) °F(°C)

Evaporator leaving dry bulb air temperature

°F(°C) °F(°C)

Refrigerant line length:

Circuit A

Circuit B

____ Liquid

____ Liquid

____ Suction ____ Suction

Hot gas bypass installed: ____ Circuit A ____ Circuit B

Leak tested PSIG:

____ Circuit A ____ Circuit B

Hold time: ____ Circuit A ____ Circuit B

Total lbs of R-410A added: ____ Circuit A ____ Circuit B

Breaker & fuses rating:

_____V

_____A

Voltage imbalance:

_____%

Compressor running forward _____Y

_____N

Outdoor Air Temperature:

_____°F(°C)

Compressor Amperage

_____Circuit A _____Circuit B