Before hoisting the array to its operating position recheck the

actual status of the assembly as follows:

Note: When applicable, the same system and safety checks

also apply to ground stack assemblies.

4.1. Mechanical setup

Check the attachment of the Load adapter(s) to the Flying

frame and ensure all Locking pins are properly inserted and

locked.

Check the attachment of the secondary safety device at the

Flying frame (refer to section Þ Chapter 2.8. "Secondary

safety" on page 16).

Check the attachment of the Flying frame(s) to the cabinets

and ensure all Locking pins are properly inserted and locked.

Check the attachment of all Front links on both sides of the

cabinets and ensure all Locking pins are properly inserted and

locked.

Check the splay angles and the attachment of the Splay/Rear

links on the rear of the cabinets and ensure all Locking pins

are properly inserted and locked.

In "Single pickpoint operation" check the desired total vertical

aiming of the entire array using an inclinometer.

4.2. Wiring

Check the wiring.

If the amplifiers are already wired and powered on, use their

System check functions or Channel mute switches and a test

signal to check the correct operation and routing of all

channels and cabinets.