TRANSPORT AND STORAGE

2.1 Consignment receipt and unpacking


Immediately after receipt of the equipment it must be
checked against the delivery/shipping documents for
its completeness and that there has been no damage
in transportation. Any shortage and/or damage must
be reported immediately to Flowserve Pump Division
and must be received in writing within ten days of
receipt of the equipment. Later claims cannot be
accepted.

Check any crate, boxes or wrappings for any
accessories or spare parts that may be packed
separately with the equipment or attached to side
walls of the box or equipment.

Each product has a unique serial number. Check
that this number corresponds with that advised and
always quote this number in correspondence as well
as when ordering spare parts or further accessories.

2.2 Handling


Boxes, crates, pallets or cartons may be unloaded
using fork lift vehicles or slings dependent on their
size and construction.

2.3 Lifting

A crane must be used for all pump sets in

excess of 25 kg (55 lb). Fully trained personnel must
carry out lifting, in accordance with local regulations

Pumps and motors often have integral

lifting lugs or eye bolts. These are intended for use in
only lifting the individual piece of equipment.

Do not use eye bolts or cast-in lifting

lugs to lift pump, motor and baseplate assemblies.

To avoid distortion, the pump unit

should be lifted as shown.

Care must be taken to lift components

or assemblies above the center of gravity to prevent
the unit from flipping.

2.3.1

Lifting pump components


2.3.1.1

Casing [1100]

Use a choker hitch pulled tight around the discharge
nozzle.

2.3.1.2

Bearing holder [3830]

Group B and 2: Insert an eye hook in the drilled and
tapped hole located on the outside diameter of the
bearing holder. Use either a sling or hook through
the eye bolt.

2.3.1.3

Bearing housing [3200]

Group B and 2: insert either a sling or hook through
the lifting lug located on the top of the housing.

2.3.1.4

Power end

Same as bearing housing.

2.3.1.5

Bare pump

Horizontal pumps: sling around the pump discharge
nozzle and around the outboard end of the bearing
housing with separate slings. Choker hitches must be
used at both attachment points and pulled tight. Make
sure the completion of the choker hitch on the discharge
nozzle is toward the coupling end of the pump shaft as
shown in Figure 2-1. The sling lengths should be
adjusted to balance the load before attaching the lifting
hook.