For LP 8/10kVA:
8. Remove all links between the terminals.
9. Split both the load wires and spread one wire over

terminal 1-2 and the other over 3-4 respectively.

10. Connect the ground wire to terminal 5. Ground

connection is essential! See figure 15a.

11. Return to either 4.5.1.1 step 5 or 4.5.1.2 step 5


4.5.4 Input/output voltages: Software modification.

NOTE:

following this procedure you realize that the values shown in the LCD match the actual

input/output voltages.

1. Switch on the circuit breakers 'utility' (8) and 'bypass' (9) (see also section 5.2, step 1-2)

2. Go to the set-up menu. See 5.3.4 ‘Set-up Menu’


3. Using the push-buttons 'up' and 'down' you can scroll through the several set-up screens. 'Enter/Reset'

confirms the screen choice. Go to the set-up screen 'INPUT VOLTAGE'.





4. Here you can change the input voltage to 240 Volt. The value of the input voltage blinks. Scroll through its

settings by using the push-buttons 'up' and 'down', the new setting is confirmed by pressing 'Enter/Reset'.





5. Go to the set-up screen 'OUTPUT VOLTAGE'.




6. Here you can change the output voltage to 240 Volt. The value of the input voltage blinks. Scroll through

its settings by using the push-buttons 'up' and 'down', the new setting is confirmed by pressing
'Enter/Reset'.



7. To return to the default screen scroll to the set-up screens first and press 'Enter/Reset'. You can also wait

20 seconds: the time-out period of no key activity.

8. You can now proceed with 5.1 or 5.2.

SETUP SCREENS
ENTER/RESET exit

INPUT VOLTAGE
208V

INPUT VOLTAGE
CHANGE TO

240V

OUTPUT VOLTAGE
208V

INPUT VOLTAGE
CHANGE TO

240V

Figure 15a. Output cable splitting for

8/10kVA 120V 2-wire