Install Converters

Step

Action

1.

Connect your personal ESD strap to the ESD jack on the left of a converter shelf before

removing the Converters from their anti-static wrap:

Figure 20 ESD Jack

2.

Remove the Converter from its shipping container.

3.

Install the Converter into the Shelf.

1. Align the plastic converter housing on the right with the card guides at the top and bottom of

the slot.

2. Slide the converter into the slot.

3. Push firmly seat the converter until the converter latch engages.

Figure 21 Converter Installation

4.

Repeat from Step 2 for remaining Converters.

5.

Install empty slot fillers into all unused slots of multi-shelf Converter Shelf Stacks.

Apply DC Power

Fault LEDs will flash red until communications is established between the system components. – see Verify Normal

States for details.

Step

Action

1.

Apply DC power by turning on circuit breakers and inserting fuses feeding both Fan Shelves and the

Converter Shelves.