9.1

Initial Startup and Local Verification

To confirm successful hardware installation before leaving the installation site, verify network connectivity

and correct hardware interconnection.

To Verify Network Connectivity:

The DS and REG LEDs on the front of the DSM3 Series should be ON solid green. This indicates

successful registration with the headend. In addition, the RF LED should also be ON solid green

indicating proper RF power levels and the ALM/RDY LED should be blinking green for normal

operation.
With the DSM3 Series used in conjunction with the XM2-HP power supply, network connectivity

can be verified via the smart display. For other power supply models, verify the network status via

the Ethernet port.
Connect a computer’s network port to the Communications Module’s Ethernet port using a

standard network cable. Launch an Internet browser and enter 192.168.100.1 into the Address.

The Communications Module will return the Web page shown below. Click on “General” to display

the key communications parameters including upstream and downstream power levels and the

cable modem’s IP address, which confirms connectivity.

9.0 Start Up and Verification

Fig. 9-1, Communications Section - General Page