Pre Start Checks

Water Flow

Make sure that you have the correct water flow rate before turning the unit on. (Refer to commissioning documentation)

CAUTION

If the unit is operated without water the unit will be damaged.

Shut Off Valves

All shut off valves must be opened prior to starting unit.

Electrical Power Supply

The power supply to the unit must be correct to design. The three phase power must be of correct phase orientation. A

permanent single phase supply (L4) provides power to the microprocessor and evaporator trace heater.

IMPORTANT

Check phase rotation of electrical supply prior to running the compressor as it’s direction sensitive.

Visual Inspection

Check that the unit is of satisfactory condition and that it’s not damaged.

CAUTION

A damaged component could indicate a reason why the unit is not operating. For example: A refrigerant leak etc.

Electrical Overloads

Check that circuit breakers are all turned on. If not investigate why they have tripped. This could be the reason why the

unit has turned off.