Maintenance, General inspections, Maintenance 125 – Airedale TurboChill FreeCool 200kW - 1830kW User Manual

Page 125: Chillers turbochill™ air cooled and freecool

Advertising
background image

125

Chiller Technical Manual 7525355 V1.0.0_04_2013

M

ain

te

nanc

e

Chillers

TurboChill™ Air Cooled and FreeCool

Operational Maintenance checks

Owners Responsibility

To ensure that the chiller can be maintained correctly ensure the following requirements are met.

Maintain a safe working environment around the chiller, free from obstructions and debris.
The unit shall follow the maintenance schedule below as a minimum.

CAUTION

The equipment contains live electrical and moving parts, ISOLATE prior to maintenance or repair work.

Ensure lock off procedures are carried out accordingly.

If inverter driven pumps are used ensured at least 5 minutes is allowed for them to discharge any electrical charge.

Service Tools / Test Equipment

Touch-up Paint

Stiff Brush

Safety Equipment

Safety Glasses / Goggles

Maintenance

General Inspections

Procedures

Task

Frequency

General Inspections

3 Mths

12 Mths

60 Mths

Check for visible mechanical damage to unit.

Visually inspect the unit for general

wear and tear, treat metalwork.

Rust should be inhibited, primed and

touched up with matching paint.
Check for excess vibration from

other rotating equipment.

Clean Microchannel condenser coil

Coil Cleaning

To clean micro channel condenser coils use detergent and a stiff bristled brush.

For heavy dirt, use either a high pressure water with a broad spray pattern or a non acidic cleaner (Ph ≥7 <10.5).

Do not steam clean.