T-armor, Eave transition (knee cap) – Metal Sales T-Armor Series User Manual

Page 59

Advertising
background image

© Metal Sales Manufacturing Corporation / Subject to change without notice 09/14

59

T-ARMOR

EAVE TRANSITION (KNEE CAP)

INSTALLATION NOTES

NOTE:

Longer Pop Rivets may be required depending on the

thickness of the materials being used.

1. Field-notch the panel ribs and bend pan of panel.

2. Set panel on the roof substrate and apply panel clip 6"

maximum from the end of the roof.

3. Apply four rows of Tube Sealant (2 on either side of the

cut) up the side of the panel rib.

4. Field-cut and bend T-Armor Rib Covers (2 required for

each rib), and fasten with 5 Pop Rivets per connection.

5. Field-notch panel Cap and bend, set on top of panel rib

and hand crimp into place.

6. Fill any gaps or opening with Tube Sealant.

Panel Clip w/ (2) #14-13 Deck Screws
T-Armor Panel (field cut and bend)

Tube Sealant (between panel ribs)

1

/

8

"x

3

/

16

" Pop Rivet (5 per assembly)

Tube Sealant

T-Armor Cap

T-Armor Rib Covers (Field cut and bend)
Bearing Plate
Moisture Barrier (by others)

Panel Clip w/ (2) Screws (by others)

Bent Angle (By others)
Rigid Insulation (By others)

Metal Decking (By others)

T-Armor Cap (Field-notch and bend)

1

/

2

:12 Slope

Minimum

9" max

T-Armor Rib Cover (Field-notch and bend)

8"

Advertising