T-armor, Ridge/hip - floating – Metal Sales T-Armor Series User Manual

Page 74

Advertising
background image

© Metal Sales Manufacturing Corporation / Subject to change without notice 09/14

T-ARMOR

74

RIDGE/HIP - FLOATING

INSTALLATION NOTES

1. Once panels have been installed, apply a row of Double

Bead Tape Sealant across panel, up and over all ribs

approximately 2" to 3" from panel end.

2. Field-cut Z-Closure to fit between the panel ribs, install

Z-Closure over Tape Sealant. Before continuing, make

sure Z-Closure placement will accommodate SSR Ridge

flashing.

3. Once Z-Closure is set in Tape Sealant, fasten through

Z-Closure, Tape Sealant and T-Armor panel with

9

/

32

"

Bulb-Tite Rivets and one #12-14x1" Self Driller N/W

screw in the rib (see page 52 for number of fasteners

required).

4. Install SSR Ridge flashing by applying Double Bead Tape Sealant to the top of the Z-Closures, locating the

SSR Ridge and securing with 3 Pop Rivets per panel.

5. If two or more flashings are required, lap the flashing over the previously installed flashing by a minimum of

2" placing a bead of Tube Sealant between the flashings and secure with Pop Rivets, 2.5" oc.

Moisture Barrier (by others)

Double Bead Tape Sealant

1

/

4

"-14 x

7

/

8

" Stitch XL (3 per panel)

Clip w/ (2) #14-13 Deck Screws

Bearing Plate

SSR Ridge

Panel Turn Up

Double Bead Tape Sealant

#12-14x1" SD N/W (1 per rib)

Z-Closure (see Page 75)

T-Armor Panel

CL

1

/

2

:12 Slope

Minimum

*Can only be used with the

low and high clip systems

9

/

32

" Bulb-Tite Rivet (see page 52)

Metal Decking (By others)

*Panel cap not shown for clarity

9" max