INSTALLATION NOTES

1. Install Eave Plate and fasten through the wood blocking

into the metal deck with #14-13 Deck Screws at 1'-0" oc.

If more than one Eave Plate is required then butt the ends

together.

2. Place panels on to the Eave Plate and apply a row of

Double Bead Tape Sealant across panel, up and over all

ribs approximately 2" to 3" from panel end.

3. Field-cut Z-Closure to fit between the panel ribs, install

Z-Closure over Tape Sealant. Before continuing, make

sure Z-Closure placement will accommodate

7" Ridge/Hip Cover.

4. Once closure is set in Tape Sealant, fasten through

Z-Closure, Tape Sealant, T-Armor panel and into the Eave Plate with #12-14x1" Self Driller N/W screws (see

page 75 for number of fasteners required).

5. Install 7" Ridge/Hip Cover by applying a bead of Tube Sealant to the top of the Z-Closure, setting the flashing

in place by hooking onto the Z-Closure.

6. If two or more flashings are required, lap the flashing over the previously installed flashing by a minimum of

2" placing a bead of Tube Sealant between the flashings and secure with Pop Rivets, 2.5" oc.

Moisture Barrier (by others)

Wood Blocking (by others)

Tube Sealant

Clip w/ (2) #14-13 Deck Screws

7" Ridge/Hip Cover

Panel Turn Up

Double Bead Tape Sealant

#12-14X1" SD N/W (1 per rib)

Z-Closure (see Pg 75)

#14-13 Deck Screws (1'-0" oc)

Bearing Plate

Metal Decking (by others)

Eave Plate

#12-14x1" SD N/W (see Pg 75)

T-Armor Panel

CL

1

/

2

:12 Slope

Minimum

Additional #14-13 Deck

Screws may be required for

areas with large snow loads

*Panel cap not shown for clarity

9" max